PlanningKitchen

How long is a kitchen remodel? A realistic Bellingham timeline.

Plan on about 5 to 9 weeks of on-site work for a full kitchen, plus a cabinet lead time before we start. Here is the real week-by-week, and how we sequence to keep your kitchen-less stretch short.

The honest answer is that a full kitchen remodel in Bellingham takes about 5 to 9 weeks of on-site work. A refresh that keeps the layout is on the shorter side. A bigger remodel that moves walls and plumbing runs longer. And before any of that, there is a planning and ordering stretch, because cabinets take weeks to arrive. The single most common reason a kitchen "takes forever" is that someone started demo before the cabinets were ordered.

We are a local kitchen and bath crew, and we would rather set a realistic expectation than promise you two weeks and blow past it. Below is how a real Bellingham kitchen project flows, week by week.

Before the clock starts: design and ordering.

This part happens before we ever swing a hammer, and it is where the schedule is really won or lost.

The key move here is that we order cabinets first and only start demo once the delivery date is close. That way your kitchen is not torn apart for weeks waiting on a box truck. It feels slower up front, but it makes the part where you live without a kitchen much shorter.

The on-site weeks, in order.

Week 1: demo

We protect your floors and the path through the house, then tear out the old kitchen, cabinets, counters, flooring, and haul it away. In older Bellingham homes this is also when we find out what is behind the walls, so it is when surprises surface. We open up, assess, and adjust the plan if needed.

Week 2: rough-in and inspection

The plumber and electrician run any new lines and circuits for the new layout, the island, and the appliances. If we are moving a wall, framing happens now. Then the city inspector checks the rough-in while everything is still open. We plan this to pass on the first visit so the schedule does not stall.

Weeks 3 to 4: walls closed, floor in, cabinets set

Once the rough-in passes, walls get closed and finished, and the new flooring goes down. Then the cabinets, which have arrived by now, get set and leveled. This is the week the kitchen starts to look like a kitchen again.

Week 5: countertops

Counters can only be measured (templated) after the cabinets are installed and level, then they are fabricated and installed a week or so later. That is why counters land mid-project, not at the start. The sink and faucet go in once the counters are set.

Weeks 6 to 8: finish work

Backsplash tile, lighting and electrical trim-out, the range hood, appliance hookups, hardware, and all the small finish details that make the kitchen feel done. This is detail-heavy and not worth rushing.

Final: punch list and walkthrough

We walk the whole kitchen with you, fix any last items on a punch list, schedule the final inspection, and hand it back clean. Then it is your kitchen again.

The honest part: you will be without a kitchen.

There is a stretch in the middle, usually from demo through the cabinets and counters going in, where you do not have a working kitchen. For most full remodels that is roughly two to four weeks. We will not pretend otherwise. What we do is sequence the work so that stretch is as short as it can be:

What makes a kitchen take longer.

A few things reliably stretch the timeline, and knowing them up front helps you plan:

Frequently asked questions.

How long does a kitchen remodel take in Bellingham?

A full kitchen remodel in Bellingham takes about 5 to 9 weeks of on-site work. A refresh that keeps the existing layout is on the shorter end, while a remodel that moves walls and plumbing runs longer. On top of that, plan for a design and cabinet-ordering stretch before demo, since cabinets take five to seven weeks to arrive.

Why do kitchen remodels take so long before work even starts?

Cabinets and countertops are made to order. Cabinets typically take five to seven weeks to build and deliver, and counters can only be templated after the cabinets are set. Smart contractors order cabinets the day you approve the layout and start demo only when delivery is close, so your kitchen is not torn apart while you wait on materials.

How long will I be without a kitchen during the remodel?

For most full kitchen remodels, the stretch without a working kitchen runs roughly two to four weeks, from demo through cabinets and countertops being installed. A good crew shortens it by ordering materials early, stacking the trades back to back, and helping you set up a small temporary kitchen so the weeks are livable.

What makes a kitchen remodel take longer than expected?

Moving walls and plumbing, surprises in older Bellingham homes like knob-and-tube wiring or galvanized pipe, custom cabinets with long lead times, and mid-project changes to the layout or finishes all add time. Locking the design and finishes before demo is the single best thing you can do to keep the schedule on track.

Want a real timeline for your kitchen?

Tell us about your project. We'll reply within 15 minutes during business hours.

Get my free quote

Keep reading.

Call Now Free Quote